Temecula residents challenge Powerlink project; SDG&E cites regional energy needs
Valley News covered the August 26 open house at Embassy Suites, where hundreds turned out to a ballroom set for 250, and quotes Save Temecula president Mark Winkler calling the session “nothing more than a perfunctory exercise.” SDG&E told the paper that transmission constraints “can lead to congestion on the grid, higher costs, and reduced reliability during extreme weather or emergency conditions.” The article also restates SDG&E's schedule — a CPUC filing in fall or winter 2026, permitting through 2029, construction from fall 2029, and service beginning in 2032 — the same dates the utility has presented to the City.